If the team discovers mid-sprint that a key dependency may slip, what is the best immediate action consistent with Scrum guidance?

Answer

Escalate and collaborate with stakeholders to remove or reduce impact

Explanation

Scrum encourages surfacing problems as soon as they are found and collaborating to reduce impact. Ignoring or waiting delays adaptation and harms predictability.