If the team discovers mid-sprint that a key dependency may slip, what is the best immediate action consistent with Scrum guidance?
Answer
Escalate and collaborate with stakeholders to remove or reduce impact
Explanation
Scrum encourages surfacing problems as soon as they are found and collaborating to reduce impact. Ignoring or waiting delays adaptation and harms predictability.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
Which change most directly helps the Product Backlog remain transparent and useful according to the scenario?
View question →
What is the most accurate statement about the Sprint Goal?
View question →
A Product Backlog item is estimated and then later understanding changes. Which principle best explains what should happen next?
View question →
In the scenario, what is the Scrum value most directly challenged when the team members avoid surfacing impediments?
View question →
In Scrum, what is the best interpretation of “Done”?
View question →
After Sprint Review, a stakeholder asks for more scope, but the team completed the Sprint Goal and wants to keep the work stable. What is the most Scrum-consistent response?
View question →