In the scenario, what is the Scrum value most directly challenged when the team members avoid surfacing impediments?

Answer

Courage

Explanation

Avoiding impediments undermines Courage to raise problems early, even when it is uncomfortable. It also reduces the team’s ability to improve outcomes.

Last reviewed: October 2026

Reviewed by FirstInTest Editorial Team

Report an error

Related questions

Which change most directly helps the Product Backlog remain transparent and useful according to the scenario?

View question →

What is the most accurate statement about the Sprint Goal?

View question →

A Product Backlog item is estimated and then later understanding changes. Which principle best explains what should happen next?

View question →

If the team discovers mid-sprint that a key dependency may slip, what is the best immediate action consistent with Scrum guidance?

View question →

In Scrum, what is the best interpretation of “Done”?

View question →

After Sprint Review, a stakeholder asks for more scope, but the team completed the Sprint Goal and wants to keep the work stable. What is the most Scrum-consistent response?

View question →

QuestionBack to list
FirstInTest

A world-class coach for every exam.

Product

CoursesVideosPricingNewsBlogFeedback

Company

About usFAQEditorial PolicyContact usFeedbackCommunityFor AI Assistants

Legal

Editorial PolicyTermsPrivacyRefunds