A risk is identified: a third-party API may change endpoints, breaking your integration. The team wants to reduce uncertainty. Which risk response strategy is most appropriate?
Answer
Mitigate by designing an abstraction layer and adding early endpoint-change monitoring
Explanation
Mitigation targets reducing probability and/or impact through proactive engineering controls and monitoring.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
During project planning, two stakeholders disagree on whether a requirement is truly within scope. Which action best applies disciplined requirements management to resolve the ambiguity?
View question →
Which matrix best supports a stakeholder engagement approach when influence and interest vary over time and the plan must be updated accordingly?
View question →
A project team uses OKRs but observes that their quarterly objectives keep shifting, causing thrash. What should the project manager do first to stabilize execution while keeping alignment?
View question →
You manage a cross-functional project using a hybrid approach. Delivery milestones depend on external procurement lead times. Which planning practice most directly improves predictability while managing dependencies?
View question →
Read the scenario and choose the best risk analysis conclusion.
View question →
A team is preparing for a milestone review. The project manager notices that some deliverables are technically complete but lack documentation required for acceptance. What is the most appropriate action?
View question →