You manage a cross-functional project using a hybrid approach. Delivery milestones depend on external procurement lead times. Which planning practice most directly improves predictability while managing dependencies?

Answer

Create dependency tracking with procurement milestones and add contingency buffers based on historical variability

Explanation

Tracking external dependencies with milestone-based controls and contingency buffers improves schedule reliability under uncertainty.