Read the scenario and choose the best risk analysis conclusion. A vendor contract includes a service-level target, but your project timeline assumes the vendor will meet it. Historically, similar vendors meet the target 70% of the time. If the vendor misses, your internal QA will extend by 5–7 days and could cause a release slip. The team debates whether to budget only the average delay. The project manager requests a probability-weighted estimate and contingency plan, including an early integration test and fallback options.
Answer
Use the probability of meeting the SLA to perform a probability-weighted estimate and plan mitigation/fallback
Explanation
SLA reliability uncertainty requires probability-weighted impact analysis; mitigation and fallback reduce both likelihood and consequences of misses.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
During project planning, two stakeholders disagree on whether a requirement is truly within scope. Which action best applies disciplined requirements management to resolve the ambiguity?
View question →
Which matrix best supports a stakeholder engagement approach when influence and interest vary over time and the plan must be updated accordingly?
View question →
A project team uses OKRs but observes that their quarterly objectives keep shifting, causing thrash. What should the project manager do first to stabilize execution while keeping alignment?
View question →
You manage a cross-functional project using a hybrid approach. Delivery milestones depend on external procurement lead times. Which planning practice most directly improves predictability while managing dependencies?
View question →
A team is preparing for a milestone review. The project manager notices that some deliverables are technically complete but lack documentation required for acceptance. What is the most appropriate action?
View question →
A risk is identified: a third-party API may change endpoints, breaking your integration. The team wants to reduce uncertainty. Which risk response strategy is most appropriate?
View question →