Read the scenario and choose the best risk analysis conclusion. A vendor contract includes a service-level target, but your project timeline assumes the vendor will meet it. Historically, similar vendors meet the target 70% of the time. If the vendor misses, your internal QA will extend by 5–7 days and could cause a release slip. The team debates whether to budget only the average delay. The project manager requests a probability-weighted estimate and contingency plan, including an early integration test and fallback options.

Answer

Use the probability of meeting the SLA to perform a probability-weighted estimate and plan mitigation/fallback

Explanation

SLA reliability uncertainty requires probability-weighted impact analysis; mitigation and fallback reduce both likelihood and consequences of misses.